Friday, September 11, 2009

Day 72

There was lots of activity today. The roof trusses were being installed on the completed sections of the cement walls while the next "lift" of cement was being poured into the other wall sections. With the crane and the cement pump truck operating at the same time, even the area above the construction site looked busy.




It was a day for aerial acrobatics as the crane manoeuvered trusses while the cement pump was operating



The trusses of the roof system are going up quickly



A view of the framing work through a window opening