Day 79

Another milestone today as the final lift of cement is poured into the exterior walls around the fine arts room and the multi-purpose auditorium. This means that the rest of the trusses should start to be installed this coming Tuesday.

As you can see from the pictures, while the Nienhuis crew is working on pouring the exterior walls, the framers were busy sheeting the roof and building the facia to match the existing building.




The top portion of the walls of the auditorium are braced for the final lift of cement



A view of the truss system from the fine arts room



The sheeting and fascia line up perfectly with the existing building