The classrooms are complete. And I do mean complete. The projectors are installed along with the sound assist systems and our cleaning crew has made the rooms sparkle!
The carpeting has been installed in the office area and the phone system is working like a charm. The floor in the auditorium has been poured but is going to take longer than planned to cure. This means that only "stocking feet" will be allowed for a while.
The fine arts area is the last area to receive attention as the crew literally works it way out of the building. But even here, the change is dramatic. The stage curtains have been hung, the floor is pretty much complete and the sinks are ready to be installed.
The railings have all been installed at the entrances and the ceramic tile in the bootroom looks great.
The pre-occupancy inspection is scheduled for this coming Thursday so we should be ready to go for the Celebration Dinner & Ribbon Cutting on Saturday.