Thursday, January 21, 2010

Day 204

The cabinetry is now being installed in the classrooms. The ceiling tiles are being put in around the perimeter of the classrooms and hallway leaving room for the finishing electrical and mechanical work. Final coats of drywall mud have been applied to the auditorium and the air is filled with drywall dust from all the sanding. Most of the exterior doors now have locks on them and the exterior pot lights are installed in the soffit.




Classroom cubbies



Storage cabinets at the back of a classroom



The auditorium is almost ready for primer




Heating ducts in the fine arts room



Ceiling tiles along the hallway



Exterior pot lights in the soffit