Day 100

The first snowfall of the season arrived before we were able to get all the shingling done. As soon as the weather warms up, we will get the roofing done so that we can move forward with pouring the cement floor. In the meantime, crews are flattening the floor in preparation for the styrofoam insulation. This insulation will be covered with poly and rebar before the water lines are placed for the in-floor heat.




The masonry work around the windows is complete



The dirt is flattened before the styrofoam sheets are placed over top



The brick work is identical to the existing building