Day 28

The ICFs arrived today and work got started putting them together to create the foundation wall system. Once they are put together, rebar is inserted to provide necessary tensional strength and then concrete is poured in the opening. We are hoping to start pouring the cement after the long weekend.

While the ICF crew was working, the final gravel layer for the fire access road was being compacted using a steam roller (I guess "road roller" would be more accurate).


The ICFs have arrived.



The ICFs are placed along the footing to create the grade beam.



Here is a closer look at the ICF grade beam.



Adding the final touches to the fire truck road.